The following is a general outline of the architectural design process we follow for a new home. We will modify our services as necessary to respond to the unique conditions of each project we design, however, this outline will convey a typical role we can play in helping you to realize your new home.
PHASE I: PRE DESIGN: (Typically charged at and hourly rate)
PHASE II: SCHEMATIC DESIGN (15% of the total fee.)
PHASE III: DESIGN DEVELOPMENT (20 - 25% of the design time.)
PHASE IV: CONSTRUCTION DOCUMENTS (30 - 35% of the total fee.)
PHASE V: BIDDING AND NEGOTIATION (5% of the total fee.)
PHASE VI: CONSTRUCTION ADMINISTRATION (25% of the total fee.)
PHASE I: PRE DESIGN: (Typically charged at and hourly rate)
Our initial efforts work to determine the options you have for developing your project under the restrictions imposed by local zoning and other regulatory bodies. We research and document the setbacks, height and area restrictions and any other governing bi-laws, which may influence the direction of your project. We generate a preliminary Building Code review and bring to your attention any unusual restrictions you may face. We often coordinate the surveying of your property. If we determine that you should further consult a civil engineer or legal professional, expert in a particular challenge of your project, we can act as your liaison to represent your interests and priorities. Depending on the particular scope of your project, we typically conclude this portion of our services with a written and graphic presentation of our findings.
Once we have determined the site conditions of the project, we begin working with you to develop a program for your new home. In a very general way we discuss the types and sizes of rooms, the style and materials you wish to incorporate, the priority of views and solar access, and any other important aspects you wish to include. We may loan you books and other resources, which will aid in articulating your desires and concerns. We discuss and clarify your budget, and study it in relation to your expectations at this time. We generally go through several iterations of this program, expanding and clarifying it with a set of questions each time. The result is be a written document, which all agree represents the project's intentions and goals.
Once we have identified the approximate scope of the project, we will enter into a more predictable portion of the design process. For a 2000 to 5000 square ft. home, we typically allow a period of 3 months to accomplish Schematic Design, Design Development, Construction Documents and Bidding and Negotiation. This period is adjusted to fit the particular needs of each project, but we find this pace to allow the client to feel in control of the process and have the time necessary to digest the hundreds of decisions, which must be made.
Top
PHASE II: SCHEMATIC DESIGN (15% of the total fee.)
In Schematic Design your program and vision will evolve into a graphic representation, merged with the influences of your site and local regulations. We begin by meeting you at your site and further discuss the possibilities of your home as it relates to the unique features of the land. We photograph the site and document any information we need to aid us in the siting of your new home. We synthesize the information generated in Pre Design into a coherent Schematic Design, which we present to you using 1/8th scale plans and elevations. The first presentation is a working meeting that often provokes plenty of discussion and comments from you. The first ideas will remain loose to allow you to participate in the process
Following this meeting, we reexamine the design, modifying and clarifying it in response to your feed back. We prepare a second set of 1/8th scale plans, elevation and sections. We study and represent the projects relationship to the land, it's access and any integral outdoor spaces. We discuss and select structural and material systems which are integral to achieving your vision. At the second presentation, we provide you with a written Statement of Probable Construction Cost based on a comparable square foot take-off. Depending on the complexity of the project, we may require a third iteration and presentation before proceeding with the design.
Top
PHASE III: DESIGN DEVELOPMENT (20 - 25% of the design time.)
The Design Development Phase serves to take the Schematic Design and expand upon it to contain all of the details and attributes, which will accommodate your lives. This phase becomes the most demanding on our clients, as many difficult decisions must be made. We develop the scheme into 1/4" per foot plans, elevations and sections. Exterior elevations and principle interior elevations are studied and resolved. We begin to discuss finish materials and look more closely at demanding areas such as the living room, the kitchen and bathrooms. We discuss and assess value to a number of functional issues including, heating and cooling options, structural systems, communications cabling, lighting systems, low maintenance materials and site issues. We hold several meetings during this period and call on you often, as questions arise and the project achieves more resolution. We make any necessary presentations to local authorities, and confirm that your project will meet all local regulations. We conclude this period with a revised Statement of Probable Construction Cost, which reflects the additional detail and insight we have achieved to date.
Top
PHASE IV: CONSTRUCTION DOCUMENTS (30-35% of the total fee.)
The Construction Document Phase produces a set of drawings and written material which convey the scope of the project in enough detail to have a contractor accurately predict the cost of the construction.
Top
PHASE V: BIDDING AND NEGOTIATION (5% of the total fee.)
There are several ways to approach the bidding of you project for construction. The traditional way is to invite several qualified contractors to price the construction of your home, upon the completion of all of the construction documents. The lowest bidder is typically awarded the project. However, we often recommend an alternative approach, which we have used almost exclusively over the past few years. We first bid the job to several qualified contractors requesting a cost range, when the construction documents are 70% complete. We then interview each of the contractors and review their proposed cost breakdown. We will choose the contractor on their price, as well as the enthusiasm and insight they express for the project. We can then employ the knowledge and opinions of the contractor and their sub contractors in the final 30% of Construction Documents. We find that we develop a team relationship with the contractor, which ultimately generates a better quality, more efficient project.
Once we have identified a sub contractor, we enter the construction phase of the project. We typically estimate the construction period for a custom home to be between 6 to 10 months, depending on the complexity of the project.
Top
PHASE VI: CONSTRUCTION ADMINISTRATION (25% of the total fee)
The Construction Administration Phase primarily serves to monitor the construction of the home and assure it is being built to the standards represented in the Construction Document. However, another very important role we can play is to facilitate changes, which naturally occur as the project begins to take shape. Especially in residential design, we find that as the project moves from drawing to building, the client becomes much more comfortable and able to participate in the detail decisions. We can help to foster this participation to assure the client feels ownership of the project, while monitoring the impacts of change on the cost and schedule. We document the topics discussed at site meetings with meeting notes. We will provide aid in the selection of colors, lighting fixtures and other finish materials.
Top
|